Contract No. 1016cc, 1018cc of Rabigh Steam Power Plant Extension, Stage II, Phase III
Discipline
Power
Client
SCECO Western Region
Project Management and Site Supervision of all construction activities including design and vendor approval. Conversion 8 Nos. of 54.7MW each crude oil fired gas turbines to combined cycle units by adding waste heat boiler & steam turbine of 132MW x 2. 270,000 cubic meter per hour of water intake canal, intake pump house and discharge canal; 2 Nos. of 15MVA auxiliary station transformers; 2 Nos. of 64000 cubic meters total capacity crude oil storage tanks, piping, etc; 1 No. of MSF Desalination Plant of capacity 1 MGPD; infrastructure; high & low pressure water piping with all accessories.