ELECTRICAL REVAMPING PROJECT FOR SAMAD
Service : Oil and Gas
Discipline : Detail Design
Client : Al-Jubail Fertilizer Company
THE OVERALL PROJECT SCOPE CONSISTS OF DETAIL ENGINEERING AND DESIGN OF A NEW SUBSTATION # 802KA, MODIFICATION/EXTENSIOIN OF EXISTING SWITCHGEAR. MCC'S, SWITCHRACK ETC. IN THE SAMAD PLANT, CABLE TRAY INSTALLATION FOR CABLE ROUTING BETWEEN NEW ZAND EXISTING SUBSTATIONS, MATERIAL PROCUREMENT ASSISTNACE AND LIMITED CONSTRUCTION SUPERVISION. THE OVERALL PROJECT HAS BEEN DIVIDED INTO GROUP-1A AND GROUP- 1B IN ORDER TO COORDINATE ACTIVITIES WITH THE TURN AROUND PERIODS IN THE YEARS 2001 AND 2003 RESPECTIVELY.
COMPLETION DATE:
2003