Consists of project management, design review, construction supervision and commissioning for:
– 4 x 340 MW dry cool combined cycle blocks, each consists of 4×60 MW gas turbines, 4 exhaust heat recovery boilers and 1 x 100 MW steam turbine, all plant auxiliaries, 1.7 MGPD R.O. water desalination trains, water treatment plants, high & low pressure water piping and ancillaries.
– 20×600 MW Gas Turbine Power Plant
– 12×60 MW Gas Turbine Power Plant.
The project also includes the conversion of 1200 MW Combined Cycle Power Plant from crude oil to natural gas, including the turbine modification works as well as installation of gas treatment plant.

  • Client
    SCECO CENTER
  • Location
    Riyadh – KSA
  • Sectors
    Electrical Powers
  • Completion Date
    Phase I: 2002
    Phase II: 2002
    Phase III: 2009

Scope Of Work
Specialization

  • Construction

    Construction Supervision

  • PMO

    PMO / Program & Project Management